August 2026
School is open with very few things left to complete.
August 19, 2026

July 2026
July 27, 2026

June 2026
The classroom section is floors, ceilings, final coat of paint and beginning furniture. Other sections of the building are not far behind. The countdown to move-in day is getting closer.
June 24, 2026

May 2026
The new High School is just a couple of months from being ready for us to move in. Painting, ceiling installation, bleacher risers in the cafetorium, and many other milestones are being completed.
May 15, 2026

March 2026
Project Manager, Ty Brown, shows us around inside the new High School. Walls are getting drywall installed and primed and things are starting to
March 18, 2026

January 2026
The latest progress of the construction site
January 15, 2026

December 2025
Both classroom areas have been roofed and are closed in with exterior walls. The office / common areas are roofed and exterior walls have begun in these areas. The framing is in place for the gym and
December 15, 2025

October 2025
The main classroom section now has a roof. Cranes are working above the cafeteria and library areas. The band hall is the large white
October 15, 2025

September 2025
Your browser does not support the video tag.
September 2025
Our new High School has begun going vertical this month. Framework for the general classroom section is visible along with a firewall
September 15, 2025

August 2025
August 15, 2025

July 2025
July 15, 2025

June 2025
June 15, 2025

May 2025
May 15, 2025

April 2025
April 15, 2025

March 2025
March 15, 2025